Adani Enterprises Ltd (AEL), part of the Adani Group, today announced its results for the financial year and quarter ended March 31, 2023. “Once again, Adani Enterprises Ltd has lived up to its standing as not only India’s most successful business incubator but also one of the world’s most successful infrastructure foundries,” said Mr Gautam Adani, Chairman, Adani Group. “The past year’s results represent indisputable evidence of the strength and resilience of the Adani Enterprises Ltd’s operational and financial performance. These exceptional results also highlight our consistent track record of gestating and building critical infrastructure businesses. Our mega-scale infrastructure project execution capabilities and our O&M management skills, which are comparable to the best in the world, are strengths that we continue to derive from the Adani Enterprises Ltd’s portfolio’s diversity to create reliable long-term value for all our investors. Our focus remains on governance, compliance, performance, and cashflow generation.”
Business | Highlights |
ANIL Ecosystem | Cell line COD declared on 31st March, 2023 for new 2.0 GW plantCompleted upgradation of existing 1.5 GW module line to 2.0 GW with TOPCON Cell Technology and COD declared on 1st April, 2023 |
AAHL – Airports | Mumbai airport achieves Highest Level 4+ “Transition” of ACA on carbon management maturity |
ARTL – Roads | Completed 3 HAM road projects during FY 23Construction in full swing in remaining 10 projects 3 Border Check Posts made operational during Q4 FY23 in Maharashtra Border Check Post project |
Business | FY23 | Q4 FY23 |
ANIL Ecosystem | Modules volume up by 15% to 1275 MW | Modules volume up by 4% to 315 MW |
AAHL – Airports (Seven Operational) | Pax movements up by 103% to 74.8 Mn | Pax movements up by 74% to 21.4 Mn |
Primary Industries Mining Services | Production volume up by 7% to 29.7 MMT | Production volume up by 17% to 10.0 MMT |
Primary Industries IRM | Volume up by 37% to 88.2 MMT | Volume up by 20% to 20.5 MMT |
2. Adani Road Transport Ltd (ARTL – Roads)
Project | State | Model | Completion % |
Vijayawada Bypass | Andhra Pradesh | HAM | 44% |
Nanasa Pidgaon | Madhya Pradesh | HAM | 48% |
Kodad Khammam | Telangana | HAM | 49% |
Azhiyur Vengalam | Kerala | HAM | 30% |
Badakumari Karki | Odisha | HAM | 31% |
Panagarh Palsit | West Bengal | BOT | 35% |
Kagal Satara | Maharashtra | BOT | 3% |
Ganga Expressway – Budaun Hardoi | Uttar Pradesh | BOT | 8% |
Ganga Expressway – Hardoi Unnao | Uttar Pradesh | BOT | 7% |
Ganga Expressway – Unnao Prayagraj | Uttar Pradesh | BOT | 8% |
3. AdaniConnex Pvt Ltd (ACX – Data Center)
Data Center | Completion % |
Chennai Phase-II (Phase-I 17 MW is already operational) | 49% |
Noida | 37% |
Hyderabad | 30% |
Updates on Established Businesses for Q4 FY23
1. Adani New Industries Ecosystem
Solar Cell & Module
Wind Turbine manufacturing
2. Primary Industries
A new report has found that more than 3,100 Native American children died in U.S.…
n Nikhil Kamath Podcast, KM Birla stated, “Rs 1 crore is just not enough to…
A large police presence was reported at Monroeville Mall on Sunday afternoon after social media…
Jacqueline Guajardo, 28, was taken into custody after an Amber Alert was issued for two…
A woman was asleep on an NYC subway train in Coney Island-Stillwell Avenue station when…
Israel has ordered the evacuation of one of the last partially functioning hospitals in northern…